Garlough Environmental Magnet

Logo: Garlough Environmental Magnet SchoolThanks to the support of voters, Garlough Environmental Magnet is in the process of making renovations and repairs to its facility. We will update this page weekly as construction progresses.

UPDATE FOR JULY 3, 2019


Completed for week ending June 28, 2019
Continued new addition roof tie-in Continued interior demo Continued mechanical and electrical rough Continued new addition siding Began install of drywall Installed main entry footing and foundations Demoed cafeteria wall Construction meeting on June 26
Planned for week ending July 5, 2019
Continue new addition roof tie-in Install new roof on southeast addition  Continue interior wall framing in new additions Continue mechanical and electrical demo and rough Install new addition siding Erect main entry steel structure Continue painting and carpeting in rooms Construction meeting on July 3 July 1, 2019 Garlough 1 July 1, 2019 Garlough 2 July 1, 2019 Garlough 3 July 1, 2019 Garlough 4 July 1, 2019 Garlough 5

 


 

BUILDING PROJECTS

Academic and Program Improvements
Sitework - separate bus and parent drop-off 
Handicapped accessibility improvements
Rightsizing of kindergarten classrooms to meet guidelines
Create 1st & 2nd grade additions, renovations, and collaboration space 
Create 3rd & 4th grade additions, renovations, and collaboration space 
Addition of conference room and staff and visitor restroom at entry 
Addition/renovation to improve kitchen and serving area

Building Maintenance Improvements
Site improvements include drainage, landscape, concrete walks, and paving 
Exterior improvements include roofing, tuck pointing, sealants, and roof access 
Interior finishes include doors, toilet partitions, stage access, and gym equipment 
Mechanical improvements include plumbing upgrades
Electrical improvements include lighting, public address system, and fire alarm system



PROJECT TIMELINE
Design and Planning: June-December 2018
Construction - Exterior Additions: Late Spring-Summer 2019
Construction - Interior Renovations: Summer 2019
Completion: Late August 2019



CONCEPT DRAWING

Graphic: Garlough Floorplan identifying areas for building improvements



SUB-COMMITTEE MEMBERS
Brett Arnold
Dan Ernst
Susan Evans
Lisa Grathen
Anna Kalmi
Sheryl Kasella
Deborah Krohn
Amanda Lundmark
Jennifer Parker
Terri Petrasek
Rachel Quick
Kelli Simpson